There was a lot of excitement on Wednesday as debates in the Council meeting mentioned fully removing all cycle separators. But no – as is so usual with the NPDC – there was some additional wording.
There was a lot of excitement on Wednesday as many words used in the Council meeting spoke of fully removing all cycle separators. But no – as is so usual with the NPDC – there was some additional wording not picked up by many who were listening to the meeting.
And to be honest, with over 3 hours to make the actual decision, a lot of people had given up on listening at all.
- The decision included that Belair to Barret Road cycleways will stay as they are.
- We have attached the vote that took place with the final decision and what will actually be delivered – with another catch – so long as it can all be done for $300k and not a penny more.
Some of our team were away on a road trip this week, picking up skills from sister organisations, for how we can grow stronger as a group. We were introduced to AI and how it can help cut to the chase when sifting through lots of information – like Council Documents and Agenda’s.
You will see a slightly new format with some of our stories where we ask AI to summarise documents from questions we ask. When we use AI though, we will let people know, so it is clear where AI information is being presented.
So today, we have attached the actual Executive Summary of the meeting agenda with the Council Officers explanations of why the Belair to Barret Road section needs to stay as it is. This is from the short version, of what was in the agenda for the elected officials to decide on. (For the people who like the detail).
We asked Claude to summarise this for us.
Claude says:
These are the main reasons why the Belair to Barrett Road section wasn't put forward as an option for removing the cycle separators:
- Cost and scale of the infrastructure. The corridor is much wider along this stretch, so the separator infrastructure is much larger. That makes it more expensive to remove, and officers consider the treatments less affordable to take out.
- Compliance with NZTA standards. The infrastructure in this section already meets NZTA standards, so there is no standards-based reason to alter it.
- Easier and safer to navigate. Because it is compliant, the section is seen as easier for people driving, cycling and walking to navigate safely.
Officers treated "fully removing all cycle separators between Belair and Barrett Road" as not reasonably practicable, so it was excluded from the three options assessed in the report. Any physical change to the state highway would also need further design work, NZTA approval of any deviations from standards, a safety assessment, NZTA quality assurance and confirmed funding.
The Alliance notes:
The Belair to Barret Road part of the cycleway was the Transport Choices Programme that was funded by Central Government and delivered by the NPDC. Claude’s summary of the Council Officers agenda is that this section of the cycleway “already meets NZTA standards”, is “compliant” and users can “navigate safely”.
This made us think –
- Does that mean that the NZTA is agreeing to the rest of the cycleway being removed - because - it is not “already” compliant and isn’t being navigated safely ?
- Does NZTA agree there are “standards based” reasons to alter all but Belair to Barret Road ?
At the end of the day, the bottom line is NZTA has most of the say in the changes being made along the entire route and we are being told NZTA do not support changing the section from Belair to Barrett Road.
Perhaps the residents affected by the horrendous wait times at the Belair intersection may like to send an email to the NPDC asking for the pink coloured concrete barriers to be removed so cars can go back to turning left and right, at the same time, at this intersection.
The email address to send that feedback to is:
Please share this information with others you think may be interested.
Posted: 21 Nov 2026